SkyCiv-documentatie

Uw gids voor SkyCiv-software - tutorials, handleidingen en technische artikelen

SkyCiv Foundation

  1. Huis
  2. SkyCiv Foundation
  3. Geïsoleerde funderingen
  4. IN 1992: Handleiding voor het berekenen van de ankerlengte

IN 1992: Handleiding voor het berekenen van de ankerlengte

The development length of reinforcement is a critical parameter in structural concrete design, ensuring that reinforcing bars can adequately transfer stresses between the concrete and steel. Sectie 8.4 of EN 1992-1-1 provides the method for calculating development length to achieve proper anchorage of reinforcement. This ensures structural integrity, veiligheid, and serviceability under various loading conditions. The development length is influenced by bar size, beton sterkte, bond conditions, omslag, spatiëring, and whether the bar is in tension or compression.

The latest SkyCiv Foundation Design update supports standard hooked reinforcements, enabling precise development length checks. Users can now customize footing bar ends as straight bars, 90° hooks, or 180° hooks, ensuring flexibility for various design needs. This guide outlines the step-by-step process for determining the required anchorage length for pad footings following EN 1992-1-1 Sectie 8.4, considering relevant influencing factors to comply with code requirements.

 

Column Anchorage Length Check

Dowel bars in pad footings ensure a strong connection between the footing and columns, effectively transferring loads and maintaining structural integrity. Typisch, column pedestals are subjected to compression loads, and the required development length is calculated using the provisions under Section 8.4.

Sectie 8.4.3: Basic anchorage length (lb,rqd)

\(l_{b,rqd} = frac{ d_{b} } {4} \[object Window]{ \sigma_{sd} } { f_{bd} }\) (Eq. 1)

Sectie 8.4.4: Design anchorage length (lbd)

\(l_{bd} = \alpha_{1} \times \alpha_{2} \times \alpha_{3} \times \alpha_{4}\keer l_{b,rqd} \) (Eq. 2)
Waarbij:

fbd = Ultimate bond stress (MPa)
σsd = Design stress of the bar at the position from where the anchorage is measured from (MPa)
db = Dowel bar diameter (mm)

Available depth (l)

The available depth should be greater than or equal to the calculated required embedment of the dowel bars. This depth is checked using Equations 2, then compared to the computed development length for the utility ratio.

 

\(l = t – (omslag + d_{b,X} + d_{b,z}) \) (Eq. 3)

Waarbij:

t = Footing Thickness (mm)
cover = Bottom concrete cover (mm)
db,X, db,z = Footing bar size in the x and z directions (mm)

Anchorage Length Check For Footing Reinforcements

The SkyCiv Foundation Design module allows users to specify bar end configurations as straight or hooked bars (90° or 180°).

 

Calculating the required development length for footing reinforcements directly influences the footing’s dimensions, ensuring they are adequate to anchor the reinforcement against tensile forces. Sectie 9.8.2.2 provides a guide on determining this tensile force which is then used in the calculation of anchorage length.

Similar to what was presented in Equations 1 en 2, the tension anchorage length check uses the same formula but with varying influencing factors.

Available Anchorage Length

The SkyCiv Foundation Design module assesses the available anchorage length, lb, kan worden aangenomen dat 9.8.2.2(4). Available length must meet or exceed the governing anchorage length.

\(l_{b} = x – omslag \) (Eq. 4)

\(l_{b} \geq l_{bd}\) (Eq. 5)

 

Wil je de Foundation Design-software van SkyCiv proberen?? Met onze gratis tool kunnen gebruikers presteren betonfunderingsberekeningen zonder iets te downloaden of te installeren!

Wilross Papaya-productontwikkelaar
ontwerp voor analyse van laterale knik en ontwerp voor koudgevormd staal
Productontwikkelaar
BSc, MEng (Civiel)
LinkedIn

Was dit artikel nuttig voor jou?
Ja Nee

Hoe kunnen we helpen?

Ga naar boven